The Herald, Sharon, PA Published Wednesday, October 22, 2003

Repairs, change orders amount to $10,000

By Lauri Galentine
Herald Writer

Last-minute change orders and emergency roof repairs will drive up the cost of Lakeview Area School District's high school renovation at least $10,000.

The project was once again the main topic of discussion by the school board Monday.

With a scheduled completion date at the end of the month, directors learned about additional work that needs to be done and a change order in the auditorium area that eliminates some work but adds a few other things.

A few months ago, hallway flooring between the high school gym and the girls' locker room had to be torn up to replace a damaged sewer pipe that ran under it.

The pipe was believed to have been damaged during the construction project and therefore was not originally a part of it. That work is now complete and the floor must be repaired.

Directors awarded a $5,895 contract to level the floor and replace the tile to Knotts Interiors Inc. of Hermitage. Knotts was the lowest of three bidders.



Back to TOP // Herald Local news // Local this day's headlines // Herald Home page



Questions/comments: online@sharonherald.com

Copyright ©2003 The Sharon Herald Co. All rights reserved.
Reproduction or retransmission in any form is prohibited without our permission.

030509